Two crates showed up on Tuesday.
Plate marker to allow for CNC engraving.
Z-axis with auto torch height control.
Machine torch. The funny part is that this costs twice as much as my first Lincoln MIG welder...and it's just the torch!
Frame is waiting for the gantry.
Gantry pretty much ready to go.
Water table assembled, installing all those bolts wasn't very fun.
Electronics waiting to go.
Got the water table in, the gantry on the table and begun to do some of the preliminary wiring.

Torchmate sent me the wrong plate marker but they are sending me the correct replacement, should probably see it next week I'm guessing


Spaghetti (lame spaghetti anyways...)! Still have a few things to route through the cable carriers before I clean things up.

I've got some slats for the table cut and installed, once all that is done then the table can be squared up and levelled. Then it time to put it through it's paces!